The Central Valley Pond
Photo By Fred Ungerer

Town
officials look to alternative financing to convert Central Valley Pond into a
pool
Updated: April 23, 2009
Woodbury residents to vote May 5 on $1.4 million to fix Central Valley Pond
Updated: April 9, 2009
Critics ask: Where are the guarantees this money will fix the clarity problems?
By Elora Kalish
Central Valley - Voters in the Town of Woodbury will go to the polls May 5 to
authorize spending $1.4 million on construction at the Central Valley Pond.
This referendum was created by petition of several Woodbury citizens who believe
work on the community swimming area is moving too fast.
If voters say yes, the Town Board will have the authority to spend $500,000 from
general funds and/or parkland fees which are currently available as well as the
issuance of $900,000 in bonds.
The pond, which was only open for one day during the swimming season, requires
major improvements in order to comply with state and county Health Department
standards for a public swimming pool. County health officials classified the
Central Valley Pond as a pool in 2007.
Renovations of the swimming area would address two issues. The pool
classification requires the installation of a filtration system as well as a new
recirculation and water treatment system.
The other, more visible problem is the lack of clarity of the pool water, which
has plagued this facility for quite some time.
Riddick and Associates, the Town’s consulting engineer, has prepared a proposal
designed to overcome both of these issues.
Town Supervisor John Burke said that the county has given a preliminary approval
of these plans, so he said he is confident in asking the Town of Woodbury voters
for the funds necessary to complete the work.
The Town Board also has hired Maser Engineering to review this plan for a second
opinion, a measure designed for checks and balances and to bolster confidence in
the proposed plan.
Critics say a lot of money will be spent on a project that doesn’t guarantee the
water will be clear.
“I think they’re going too fast,” said John Smith of Highland Mills. “What if
the $1.4 million fails?”
Others share that concern. They do not feel all alternatives have been explored,
including reducing the size of the pool or challenging the pond’s pool
classification status.
“There is a misconception that we’re looking to close this facility,” said Robin
Crouse, also of Highland Mills. “We’re not; we’re supporters.”
Both Smith and Crouse insist their goal is for the voters to decide for
themselves whether to spend an additional $1.4 million on this facility after
the town spent $1.2 million back in 2006.
Burke said he is concerned about the impact of employment and enjoyment to the
town residents. The Central Valley Pond typically employs 80 people during the
summer season. Hundreds of people use the pond to cool off each day.
“We have many people who purposely have moved from other parts of the county
because of the program and facilities we have here,” the supervisor added.
If the voters approve the bond referendum, Burke expects that work will begin as
soon as possible. However, he recognizes the pool will most likely not open
before the end of July.
“I still want it done and make sure it works so clearly we’re ready to open it
up in 2010,” Burke said.
Background on the Central Valley Pond
Lack of water clarity has plagued the Central Valley Pond for some time. It used
to be algae would develop by August, thereby rendering the bottom invisible. The
water which is tested three times a day has always been safe for swimming.
In 2005, the County and State Health Departments informed the town that unless
major renovation was done, the pond could not open.
A $1.2 million construction project was completed in 2006. At that time, the
bottom of the pond, made of macadam (blacktop material), was beginning to break
up.
In the southern end of the pond, where competitive swimming lanes were housed,
the ground was soft. It was discovered that compost-like material was under the
surface and so the subsurface had to be removed and reconstructed.
The diving boards were moved to a different area where the water reached eleven
feet. A new wall, beneath the diving boards, was built to maintain safe diving.
In 2007 when the renovated pond opened, the water was clear. It would remain
that way until it rained. Then instead of algae, the water would turn an
orange-brownish color.
Chemicals would be added, the water would become clear for a few days, and then
turn again after the rain.
A young man drowned in the pond in 2007. It was determined he suffered a seizure
after he dove into the pond.
The bottom of the pond was not visible. The state then determined that a
filtration system was necessary, and the pond was then classified as a pool. The
town had until 2009 to meet public pool specifications.
Further testing reveals the orange-brownish color comes from the wall that was
constructed in 2006. The new plans for the pool include sump pumps connected to
underground pipes that will bring the water behind the wall to an overflow
instead of it flowing back into the pool. This is designed to alleviate the
problem of unclear water.
Critics of the plan say no one has said it is one hundred percent guaranteed.
Woodbury Supervisor John Burke acknowledges that this “is the closest we can get
to guarantees.”
Central Valley Pond
The entrance is located on Dunderberberg Road in Central Valley. The parking lot
is across the street from the pond and sits down the hill from the entrance of
the M-W High School. The pond is chlorinated and has a large paved and painted
surface with two diving boards and two rafts, which are anchored in the
deep-water section. A pavilion houses a large room for game playing. There are
picnic and shaded areas and a sand bottom playground area for children. A
basketball, volleyball, racquetball and tennis court are on premises and
Dunderberg Baseball Field sits above on the hill. A stage area was recently
added for weekend concerts and special events.
Source: www.townofwoodbury.com